Skip to main content
Skip table of contents

Configure Options


Configure Options

General Options

  • Include Internal Dependencies - Will either include or exclude dependencies that are of the same grouping

e.g. If you were grouping issues by Project (under Grouping Options) and toggled off this option, this would exclude dependencies where both issues belonged to the same Project.

  • Include Resolved Dependencies - Will either include or exclude dependencies where either issue has a Status Category of DONE (i.e. a green status)

  • Include Issues with No Dependencies - WIll either include or exclude dependencies that have zero dependencies associated with an issue

  • Dark Mode - Toggles the Dark Mode or Light Mode themes of the app

  • Grouping Colour Theme - Determines the themes for the following charts:

    • Dependency Summary

    • Dependency Board

    • Dependency List

    • Dependency Timeline

    • Individual Dependencies

    • Grouped Dependencies

    • Dependency Matrix

    • Dependency Network

    • Dependency Spiderweb

  • Show Mismatched Due Dates - Will display a yellow ⚠️ icon to show issues that have a linkage that is due after the original. For example, if ABC-123 (due Jan 1st) is blocked by DEF-456 (due Feb 1st), then this is considered a mismatch. This will display on the following charts:

    • Dependency Board

    • Dependency List

    • Dependency Spiderweb

  • Show Overdue Issues - WIll display a red (error) icon (but with a !) to show issues that are overdue based on their due date. For example, if ABC-123 is due on Jan 1st, but the current date is Feb 1st, then the issue is considered overdue. This will display on the following charts:

    • Dependency Board

    • Dependency List

    • Dependency Spiderweb

  • Draw Reference Line - Will draw a line highlighting the current date on the Dependency Board chart

  • Group Issues By - Will group the issues together by Project, Epic, Sprint or Fix Version

  • Group Dates By - Will group the ‘due date’ of each dependency by each issue’s Sprint End Date, Fix Version Release Date, Issue Due Date, or the Earliest / Latest of those three options

e.g. If one Project were using Sprints on a Scrum board, but another Project was using Fix Version on a Kanban board, you could use the Earliest Date or Latest Date options to align the dates of both Projects together. Nifty!

  • Periodically Refresh Data - When enabled, a full refresh of the data will be performed in the background after the initial charts are generated

  • Refresh Frequency - Determines how often the data is refreshed

Note: Be mindful that each refresh involves making several API calls, so ensure the refresh frequency is ‘sensible’!

  • Calculate Capacity - If toggled, this will add additional cells to the Dependency Board chart to show the capacity for each grouping (row) and date (column)

  • Capacity Definition - Determines how capacity is calculated. Options are Total Issues, Story Points, Original Time Estimate, or Remaining Time Estimate

‘Dependency Board’ Options

  • String Colour - Determines the string colour

  • String Thickness - Determines the string thickness

  • Edit Issue Mode - When clicking on an issue on the Dependency Board, this will either enable or disable the ability to dynamically edit the dependencies of an issue in the app itself (disabling this feature will simply load up the issue in a separate tab)

  • Root Cause Colour - Determines the colour of issues with a high ‘root cause’ value when the toggle is enabled on the Dependency Board chart

  • Place ‘Dependency String’ in front of Issues - Will place the ‘string’ either in front of, or behind the issues for the sake of controlling visual noise on the board

  • Place Issues without Due Dates in last column - Will place issues that don’t have an associated date (under Grouping Options) in either the first or last column of the Dependency Board

  • Show Issue Summary on Zoom - Sets the zoom threshold for when the Dependency Board switches between displaying the Summary and the Description of each issue

‘Dependency Calendar’ Options

  • Cell Colour - Determines the colour theme for dates with a high value of dependencies

‘Dependency Matrix’ Options

  • Cell Colour - Determines the colour theme for groups with a high value of dependencies

  • Axis Labels - Shows either the group name (e.g. Project Name) or group id (e.g. Project Key) on the X and Y axes

‘Dependency Spiderweb’ Options

  • Dependency Direction - Determines the arrow direction for issue links (i.e. ‘A blocks B' or 'B is blocked by A’)

‘Dependency CFD’ Chart Options

  • CFD Colour - Determines the colour of the Cumulative Flow Diagram (CFD) chart

  • CFD Delta Increase Colour- Determines the colour of the Cumulative Flow Diagram (CFD) Delta chart when an increase is observed for that date period

  • CFD Delta Decrease Colour - Determines the colour of the Cumulative Flow Diagram (CFD) chartCFD Delta chart when a decrease is observed for that date period

‘Time to Resolve’ Chart Options

  • PDF Colour - Determines the colour of the Probability Density Function (PDF) view on the Time to Resolve charts

  • CDF Colour - Determines the colour of the Cumulative Density Function (CDF) view on the Time to Resolve charts

Cookie Settings

  • Show Cookie Settings Dialog - Displays the Cookie Settings modal, allowing you to choose what information is captured by the tool (see our Privacy Policy for more information)



Next Steps


JavaScript errors detected

Please note, these errors can depend on your browser setup.

If this problem persists, please contact our support.